San Francisco Transbay development

San Francisco Transbay development

FieldValue
nameSalesforce Transit Center & Tower
image_size250px
locationMission Street
San Francisco, California
coordinates
statusComplete
opening2017–19
building_typeCommercial offices
antenna_spire1070 ft
roof920 ft
floor_count61
floor_area
architectCesar Pelli
engineerMagnusson Klemencic Associates
developerBoston Properties
Hines Interests Limited Partnership
references

San Francisco, California Hines Interests Limited Partnership

The San Francisco Transbay development is a completed redevelopment plan for the neighborhood surrounding the Salesforce Transit Center site, South of Market near the Financial District in San Francisco, California. The new transit center replaced the since-demolished San Francisco Transbay Terminal, and new skyscrapers, such as Salesforce Tower, took advantage of the height increases allowed through the San Francisco Transit Center District Plan. The sale of several land parcels formerly owned by the state and given to the managing Transbay Joint Powers Authority helped finance the construction of the transit center.

History

Downtown San Francisco, showing Millennium Tower (301 Mission St) center, behind it left the Salesforce Tower (under construction), far left top the 181 Fremont Street Tower (under construction), and foreground the cranes for the Park Tower (under construction) in front of the bare structure of the Transbay Terminal (under construction). From the parking lot of the Providian Financial Building / 201 Mission St, on Howard between Beale and Main.

The original Transbay Terminal opened in 1939 as the San Francisco terminus for the Key System and other commuter trains that travelled across the new San Francisco–Oakland Bay Bridge to the East Bay. Train service to San Francisco was discontinued in 1958 and the Transbay Terminal was reconfigured for buses. Transbay train service would resume in 1974 with the opening of BART and the Transbay Tube, but the BART tracks were routed under Market Street, bypassing the Transbay Terminal. By the end of the 20th century, the Transbay Terminal was underused and rundown, handling an average of about 20,000 commuters per day.

In 1985, San Francisco adopted the Downtown Plan, which slowed development in the Financial District north of Market Street and directed it to the area South of Market around the Transbay Terminal. In the early 1990s, the Embarcadero Freeway was demolished following the 1989 Loma Prieta earthquake, freeing up numerous city blocks for development south of the Transbay Terminal. In 1995, Caltrain agreed to study extending its commuter rail service from its Fourth and King terminus closer to the Financial District, including whether the obsolete Transbay Terminal should be removed, remodeled, or rebuilt.

Ultimately, it was decided that the Transbay Terminal should be rebuilt, with the rail extension entering the Terminal under Second Street. In 1996, then-San Francisco Mayor Willie Brown issued the idea of redeveloping the earthquake-damaged Transbay Transit Center. To that end, Brown tapped his then-new deputy Mayor Maria Ayerdi Kaplan to head the project. Kaplan created, and then became executive director of, the Transbay Joint Powers Authority in 2008.

To finance the projects and promote development in the area, the Transbay Redevelopment Plan was adopted by the City of San Francisco in June 2005. By raising a number of building height limits and selling former freeway parcels, the plan envisions the development of over 2,500 new homes, 3 million square feet of new office and commercial space, and 100,000 square feet of retail.

Developments

Salesforce Transit Center

Main article: Salesforce Transit Center

Designed by Pelli Clarke Pelli, the new Salesforce Transit Center replaced the former Transbay Terminal at a cost of roughly $2 billion USD and has been dubbed the "Grand Central Station of the West" by proponents. The new center is planned to eventually include an extension of the Caltrain commuter rail service into the station from its current northern terminus at 4th and King Streets in Mission Bay via tunnels which would also carry the Bay Area segment of the future California High-Speed Rail (CAHSR) and terminate at the station, as mandated by California voters in Proposition 1A, the ballot measure authorizing CAHSR construction. This extension would cost an additional $2–4 billion and is currently unfunded.

Salesforce Transit Center construction site.

The Transit Center currently has three levels plus a 5.4 acre public rooftop park. The ground level is the street entrance to the Transit Center. Above that are administrative offices, retail shops, restaurants, and the Amtrak/Greyhound waiting room. The final indoors level services Transbay buses from San Francisco's Muni, the East Bay's AC Transit, and WestCAT, as well as long-distance buses operated by Greyhound and Amtrak Thruway. Future Caltrain and HSR service would utilize two underground levels, the lower of which would house the tracks and platforms, and the upper of which would house a retail concourse and waiting areas.

Salesforce Tower

Main article: Salesforce Tower

Adjacent to the Transit Center and at the center of the redevelopment effort is a signature skyscraper at First and Mission Streets. The proposal featured plans from several major architecture firms including Skidmore, Owings & Merrill, Richard Rogers Partnership, and Pelli Clarke Pelli Architects. Eventually the plan from Pelli Clarke Pelli Architects was picked. The original plans from Pelli Clark Pelli Architects called for a 1200 ft tower as the main tower and a massive three-block-long Transbay Center. However, due to considerations about how the tower would cast a shadow over some of the city's parks, the height was eventually reduced to 1070 ft.

The designs to the supertall tower changed during its planning phase, its final design eventually incorporates slits at each side of its angular top along with an altered terminal station design. However some of the original design cues were later restored and reincorporated due to complaints about the design modifications. The tower and the new terminal had their groundbreaking ceremonies on March 27, 2013. The office tower opened in early 2018, followed by the Transit Center in August of that same year.

Increased height limits

With the adoption of the Transit Center District Plan in 2012, height limits were raised for several parcels in the vicinity of the Transit Center. Among the parcels zoned for taller buildings are 50 First Street, 181 Fremont Street, 350 Mission Street, Golden Gate University's campus at 536 Mission Street, the proposed Palace Hotel Residential Tower, and the Salesforce Tower site.

Former freeway parcels and bus ramps

Following the 1989 Loma Prieta earthquake, the Embarcadero Freeway was torn down, opening up a number of blocks for development. Several other parcels, near Beale and Howard streets, were used for the East Loop Ramp of the Transbay Terminal and are not needed for the new Transit Center. In 2007, the state of California officially agreed to transfer the state-owned parcels to the City and County of San Francisco.

The former freeway parcels are located mostly along the north side of Folsom Street between Essex and Spear and have been zoned for residential use. Other lots, called Parcel F, Parcel M, and Parcel T, have been zoned for office buildings. Parcel T is the site of Salesforce Tower. As of 2013, Transbay Joint Powers Authority has accepted proposals for Blocks 6/7 and Block 9. The first parcel developed was Block 11, also known as the Rene Cazenave Apartments, an affordable housing project located at 25 Essex Street.

ParcelZoningSoldPriceUseLocationReference
Block 1Residential2016$50.18 million400-foot Folsom Bay Tower with 391 units, including 156 affordable-rate
Block 2ResidentialTemporary Transbay Terminal
Block 3ParkTemporary Transbay Terminal; Slated to become Transbay Park
Block 4ResidentialTemporary Transbay Terminal
Block 5Residential2015$172.5 millionAlthough zoned for residential, will become Park Tower at Transbay office building250 Howard Streeturl=http://www.socketsite.com/archives/2014/04/unforeseen_circumstances_result_in_an_unexpected_transb.htmltitle=An Unexpected Transbay Twist And Block Redesigndate=April 3, 2014publisher=SocketSiteaccessdate=April 26, 2014}}
Block 6Residential2013$30 million300-foot tower with 409 market-rate units and 70 affordable units299 Fremont Street
Block 7Residential201377 units to be built by Mercy Housing
Block 8Residential2014$72 million550-foot, 740-unit residential towerurl=http://www.socketsite.com/archives/2014/03/rem_koolhaas_design_selected_for_folsom_street_tower_de.htmltitle=Rem Koolhaas Design Selected For Folsom Street Towerpublisher=SocketSitedate=March 18, 2014accessdate=April 26, 2014}}
Block 9Residential2013$43.32 million400-foot, 537-unit residential tower500 Folsom Streeturl=http://www.bizjournals.com/sanfrancisco/blog/real-estate/2013/02/avant-essex-win-transbay-block-9-bid.htmltitle=Avant, Essex win Transbay Block 9 bid}}
Block 10ParkPlanned Transbay Terminal Under Ramp Park
Block 11Residential2011120-unit Rene Cazenave Apartments25 Essex Street
Block 12Residential
Parcel FCommercial Office2016$160 million61-story, 800-foot tower, with 16 floors of offices, a 220-room hotel, and 175 condos
Parcel MCommercial Office
Parcel TCommercial Office2013$191.8 millionSalesforce Tower415 Mission Street

Transbay Joint Powers Authority

The Transbay Joint Powers Authority (TJPA) oversees the design, construction, operation, and maintenance of the Salesforce Transit Center. The charter of the TJPA includes three initiatives:

  • Replacing the San Francisco Transbay Terminal
  • Extending the Caltrain rail line
  • Redeveloping the area surrounding the Salesforce Transit Center

The TJPA was created in 2001 as a collaboration of several Bay Area government and transportation agencies. It coordinates the efforts of 11 local, regional, and statewide transit systems.

References

References

  1. (March 12, 2012). "Yes, The Proposed Transbay Transit Tower Shrank A Hundred Feet". [[SocketSite]].
  2. King, John. (August 12, 2007). "Plan B: Architects: Pelli Clarke Pelli". San Francisco Chronicle.
  3. King, John. (September 21, 2007). "'Aggressive schedule' for proposed Transbay transit center, tower (picture)". San Francisco Chronicle.
  4. "Emporis building ID 307246". [[Emporis]].
  5. {{SkyscraperPage. 41341
  6. {{Structurae. 20048908
  7. "Pelli Clarke Pelli Transbay Center & Tower Description".
  8. (November 2009). "Transit Center District Plan".
  9. Epstein, Edward. (February 16, 2001). "Ambitious Plan For Rebuilding S.F. Transit Hub / Ideas for new Transbay Terminal". The San Francisco Chronicle.
  10. (May 24, 2012). "Transit Center District Plan – General Plan Amendments".
  11. Mitchell, Eve. (August 4, 1995). "CalTrain moves a step closer to Financial District". San Francisco Chronicle.
  12. (August 26, 2018). "Maria Ayerdi-Kaplan, Salesforce Transit Center Builder, TJPA Creator: Her Story Part One". Oakland News Now.
  13. "Transbay Transit Center – Redevelopment Plan".
  14. (August 12, 2018). "Park, housing key to future of SF's new high-rise neighborhood". San Francisco Chronicle.
  15. "Transbay Transit Center – The Program".
  16. (August 9, 2018). "Salesforce Transit Center puzzle: When will the trains get to the station?". San Francisco Chronicle.
  17. "Transbay Transit Center – The Project: Transit Center".
  18. (August 7, 2007). "San Francisco's Transbay Terminal Design Proposals: Highlights". [[SocketSite]].
  19. Ferrato, Philip. (March 14, 2012). "Transbay Terminal, Still Pretty, Still Tall, Just Shorter". CurbedSF.
  20. Hromack, Sarah. (May 1, 2008). "Transbay Terminal Plan: New-and-Improved". CurbedSF.
  21. (September 24, 2012). "Transbay Tower Tweaks, Cuts And Timing". [[SocketSite]].
  22. King, John. (March 15, 2013). "Transbay center design change proposed". San Francisco Chronicle.
  23. (March 26, 2013). "Boston Properties and Hines Close on Record Land Sale for Transbay Transit Tower Parcel". BusinessWire via MarketWatch.
  24. (May 24, 2012). "Planning's Towering Transit Center District Plan Decision: Approved". [[SocketSite]].
  25. (October 26, 2006). "The Transbay Redevelopment". [[SocketSite]].
  26. (December 13, 2007). "California Transportation Commission Approves Land Transfer to TJPA, City and County of San Francisco for Transbay Transit Center Project and Redevelopment".
  27. "Office of Community Investment and Infrastructure (OCII) Transbay Project Area".
  28. "Transbay redevelopment project area".
  29. (January 10, 2013). "The Green Designs For Block 6: Folsom Street From Fremont To Beale". SocketSite.
  30. (February 15, 2013). "The Winning Design And Developer For Transbay Block 9". SocketSite.
  31. Dineen, J.K.. (April 2, 2012). "Bridge, Community Housing break ground on Transbay affordable project". San Francisco Business Times.
  32. (July 26, 2016). "Resolution 291-16". Board of Supervisors of the City and County of San Francisco.
  33. (April 3, 2014). "An Unexpected Transbay Twist And Block Redesign". [[SocketSite]].
  34. Weinberg, Cory. (July 13, 2015). "Soaring office tower approved to hit San Francisco's skyline". San Francisco Business Times.
  35. "$30 million deal will help bankroll San Francisco's Transbay Terminal".
  36. (January 9, 2013). "The Winning Bid and Plan to Develop Folsom from Fremont to Beale".
  37. "Committee/board of supervisors - agenda packet contents list".
  38. (October 31, 2013). "Transbay Block 6, New 32-story Luxury Apartments Complex, Announced in San Francisco's SoMa District".
  39. (March 18, 2014). "Rem Koolhaas Design Selected For Folsom Street Tower". SocketSite.
  40. "Avant, Essex win Transbay Block 9 bid".
  41. "Transbay Terminal Under Ramp Park". CMG Landscape Architecture.
  42. Li, Roland. (June 22, 2016). "Exclusive: Last Transbay tower site sells for $160 million". San Francisco Business Times.
  43. (March 15, 2017). "Parcel F Plans Formally Submitted to Planning". SocketSite.
  44. "Hines, Boston Properties sling ceremonial dirt in Transbay ground-breaking".
  45. (January 20, 2015). "Transbay Transit Center".
  46. "About the TJPA « Transbay Program".
Wikipedia Source

This article was imported from Wikipedia and is available under the Creative Commons Attribution-ShareAlike 4.0 License. Content has been adapted to SurfDoc format. Original contributors can be found on the article history page.

Want to explore this topic further?

Ask Mako anything about San Francisco Transbay development — get instant answers, deeper analysis, and related topics.

Research with Mako

Free with your Surf account

Content sourced from Wikipedia, available under CC BY-SA 4.0.

This content may have been generated or modified by AI. CloudSurf Software LLC is not responsible for the accuracy, completeness, or reliability of AI-generated content. Always verify important information from primary sources.

Report