NTPC Dadri
Thermal power plant in Dadri, India
Thermal power plant in Dadri, India
| Field | Value |
|---|---|
| name | National Capital Power Station |
| country | India |
| location | Gautam Budh Nagar district, Uttar Pradesh |
| image | NTPC Power Station - Aerial View - Dadri 2016-08-04 5757.JPG |
| image_caption | Aerial view of NTPC power station, Dadri |
| coordinates | |
| status | O |
| commissioned | 1991 |
| operator | NTPC |
| th_fuel_primary | Coal-fired, gas-fired |
| ps_units_operational | 1820 MW coal |
| extra | www.ntpc.co.in |
817 MW gas
National Capital Power Station (NCPS) or NTPC Dadri is the power project to meet the power demand of National Capital Region (India). It has a huge coal-fired thermal power plant and a gas-fired plant and has a small township located in Uttar Pradesh, India for its employees. It is located in Gautam Budhh Nagar district of Uttar Pradesh about 25 km from Ghaziabad and about 9 km from Dadri. It is nearly 48 km from New Delhi towards Hapur. The township has an area of about 500 acres over all. NTPC Dadri is a branch of National Thermal Power Corporation (NTPC).
Capacity
NTPC Dadri is a unique power plant of NTPC group which has both coal based thermal plant and gas based thermal plant of 1820 MW and 829.78 MW respectively and a 5 MW solar plant totaling 2654.78 MW.
Coal based
The coal for the power plant is sourced from Piparwar Mines, Jharkhand. The source of water for the power plant is Upper Ganga Canal.
| Stage | Unit number | Installed capacity (MW) | Date of commissioning |
|---|---|---|---|
| 1st | 1 | 210 | 1991 October |
| 2 | 210 | 1992 December | |
| 3 | 210 | 1993 March | |
| 4 | 210 | 1994 March | |
| 2nd | 5 | 490 | 2010 January |
| 6 | 490 | 2010 July | |
| Total | Six | 1820 |
Gas based
The gas for the power plant is sourced from GAIL HBJ Pipeline. It also supports HSD as alternate fuel. The source of water for the power plant is the Upper Ganga Canal.
| Stage | Unit number | Installed capacity (MW) | Date of commissioning | GT / ST | |
|---|---|---|---|---|---|
| 1st | 1 | 130.19 | 1992 March | GT | |
| 2 | 130.19 | 1992 May | GT | ||
| 3 | 130.19 | 1992 June | GT | ||
| 4 | 130.19 | 1992 November | GT | ||
| 5 | 154.51 | 1993 February | ST | ||
| 6 | 154.51 | 1993 March | ST | ||
| Total | six | 829.78 |
The total capacity is 2654.78 MW.
References
References
This article was imported from Wikipedia and is available under the Creative Commons Attribution-ShareAlike 4.0 License. Content has been adapted to SurfDoc format. Original contributors can be found on the article history page.
Ask Mako anything about NTPC Dadri — get instant answers, deeper analysis, and related topics.
Research with MakoFree with your Surf account
Create a free account to save articles, ask Mako questions, and organize your research.
Sign up freeThis content may have been generated or modified by AI. CloudSurf Software LLC is not responsible for the accuracy, completeness, or reliability of AI-generated content. Always verify important information from primary sources.
Report