Line 17 (Beijing Subway)
Subway line in Beijing
Subway line in Beijing
| Field | Value | ||
|---|---|---|---|
| name | Line 17 | ||
| other_name | M17 / R2 (planned name) | ||
| logo | BJS Line 17 icon.svg | ||
| logo_width | 100px | ||
| color | |||
| image | 540 reversing at Jiahuihu (20211231160259).jpg | ||
| image_width | 300px | ||
| caption | A CCD5035 train reversing at Jiahuihu station (December 2021) | ||
| [[File:BeijingMTR.svg | 100px | Beijing MTR | link=MTR Corporation#Beijing]] |
| type | Rapid transit | ||
| system | Beijing Subway | ||
| status | Operational | ||
| locale | Beijing, China | ||
| start | |||
| end | |||
| stations | 21 (20 in operation) | ||
| open | (South) | ||
| (North) | |||
| (Middle) | |||
| operator | Beijing MTR Corporation Limited | ||
| character | Underground | ||
| depot | Ciqunan and Xiejiacun | ||
| stock | 8-car Type A | ||
| linelength | 48.9 km | ||
| gauge | |||
| speed | 100 kph | ||
| map | |||
| map_state | collapsed |
(North) (Middle) Line 17 of the Beijing Subway () is a rapid transit line in Beijing, China. The line is fully underground and has a total length of 48.9 km. It opened in parts between 2021 and 2025. Line 17's color is turquoise.
The south section of Line 17 opened on December 31, 2021. The north section of Line 17 opened on December 30, 2023 (except ), and the middle section of Line 17 opened on December 27, 2025 (except ). opened on January 31, 2026 with the opening of Wangjing West Transport Hub. will open at later date due to construction of Majuan Transport Hub.
Due to the slow construction progress of the middle section ( to ), the line was divided into the northern section ( to ) and the southern section ( to ) from 2023 to 2025, until the middle section was put into operation in December 2025, completing the line.
Description
Line 17 is runs from the station in Changping District to station in Tongzhou District. The line will help alleviate congestion on Line 5, Line 10 and Line 13.
Rolling stock

Line 17 uses 8-car Type A rolling stock.
Opening timeline
| Segment | Commencement | Length | Station(s) | Name | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Shilihe — Jiahuihu | 31 December 2021 | {{convert | 15.8 | km | mi | url=https://www.mtr.bj.cn/service/line/line-17.html | title=17号线 北京京港地铁有限公司}} | 7 | |||||
| Future Science City North — Workers' Stadium | 30 December 2023 | {{convert | 24.9 | km | mi | url=https://www.takefoto.cn/news/2023/12/27/10659898.shtml | date=2023-12-27 | title=@天通苑居民,地铁进城将多一种更快选择:17换10 | author=孙宏阳 (Sun Hongyang)}} | 9 | |||
| Workers' Stadium — Shilihe | 27 December 2025 | {{convert | 8.2 | km | mi | url=http://www.rail-transit.com/xinwen/show.php?itemid=34137 | title=『北京』3条地铁新线全部进入“跑图”阶段 | quote=中段从十里河至工人体育场,约8.2公里,共设车站4座。……6号线南延作为北京中心城东西向骨干线6号线的延长线,约2.1公里……从线路图上看,18号线(马连洼—天通苑东)是一条位于城市北部东西向的骨干线路,线路途经海淀、昌平两区,约19.8公里,共设车站11座 | archive-url=https://web.archive.org/web/20251027123206/http://www.rail-transit.com/xinwen/show.php?itemid=34137 | archive-date=27 October 2025 | access-date=27 October 2025 | url-status=live}} | 3 |
| Wangjingxi | 31 Jaunary 2026 | Infill stations | 1 | Northern section | |||||||||
| Guangqumen Wai | June 2026 (expected) | 1 | Middle section |
Stations
| Station Name | Connections | Nearby Bus Stops | Distance | |||
|---|---|---|---|---|---|---|
| km | Location | English | Chinese | |||
| 487 923 昌27 昌60 昌63 顺66 顺75 | 0.000 | 0.000 | Changping | |||
| 417 923 昌38 昌39 昌63 快速直达专线8 专42 | 1.724 | 1.724 | ||||
| 301 386 432 530 596 628 夜26 专58 专119 | 5.848 | 7.572 | ||||
| 386 596 专81 | 1.935 | 9.507 | Chaoyang | |||
| 386 415 621 966 | 1.923 | 11.430 | ||||
| 450 538 547 571 851 854 866 907 928 987 专112 快速直达专线197 | 5.022 | 16.452 | ||||
| 130 132 467 515 567 939 专212 | 2.500 | 18.952 | ||||
| 95 130 132 300 300快 302 368 379 419 467 515 596 604 641 671 916快 942 980快 快速直达专线93 快速直达专线141 快速直达专线195 快速直达专线196 夜18 夜30 | 1.207 | 20.159 | ||||
| 3 18 24 110 120 123 132 359 379 401 404 515 536 675 850 850快 915 916 916快 918 935 935快 942 980快 夜18 夜24 专26 | 2.411 | 22.570 | ||||
| 3 4 39 110 113 115 117 118 120 403 406 431 夜3 夜24 夜34 | 2.324 | 24.894 | ||||
| 28 39 75 98 101 109 110 118 120 126 139 350 403 412 515 615 BRT2(快速公交2) 快速直达专线78 夜13 夜24 专5 专114 | 1.169 | 26.063 | ||||
| 1 9 28 39 58 120 126 140 403 639 668 夜1 夜24 | 1.467 | 27.530 | ||||
| — | — | Dongcheng | ||||
| 34 36 51 440 专19 | 3.909 | 31.439 | Chaoyang | |||
| 28 53 300 300快 352 368 378 439 440 513 638 649 680 687 846 848 973 975 976 985 986 995 快速直达专线217 夜30 专19 | 1.677 | 33.116 | ||||
| 378 638 976 986 | 1.672 | 34.788 | ||||
| 专217 | 2.349 | 37.137 | ||||
| 440 637 820 986 专182 专187 | 5.840 | 42.977 | Tongzhou | |||
| 913 T12 T68 T68区 专232 | 2.334 | 45.311 | ||||
| 637 820 986 T11 T27 T56 T87 专159 专207 | 1.455 | 46.766 | ||||
| 专160 专207 | 2.125 | 48.891 |
History
.jpg)
In January 2011, an official with the city's planning committee indicated that Line 17 of the subway was planned to run east–west through the city's Central Business District under Guanghua Road with transfers to Lines 4 and 5. However, the line run through Central Business District is known as Line 28 now.
In February 2012, the city's planning committee identified a different Line 17, as a line planned for 2020, that would run north–south from Tiantongyuan to Yizhuang that would run parallel and to the east of Line 5. On 15 June 2012, the city government disclosed tentatively planned stations for the line.
On 10 October 2013, city authorities confirmed that Line 17 would run from the Future Science Park North station in Changping District to Yizhuang Zhanqianqu South station in Tongzhou District.
Construction of the line began in 2015.
On 8 July 2022, an EIA document prepared by the China Academy of Railway Sciences (CARS) regarding Phase III (2022–2027) construction of the Beijing Subway announced an 8.9 km branch line of Line 17 from Tiantongyuandong Station to Beiqijia, with one intermediate station not identified.
In February 2024, Beijing Infrastructure Investment (BII) announced several tender announcements and modified the number of new stations of branch-styled phase 2 of Line 17 to 3 new stations.
References
References
- (2021-02-26). "北京今年年底预计开通7条(段)地铁 总计约54公里".
- (2023-02-07). "4段地铁6条道路陆续完工 未来科学城出行便捷度将升级".
- (2019-12-30). "确定了!北京地铁17号线,京港地铁公司运营".
- "北京地铁17号线拟2021年全线开通,为城区最长在建线路".
- (2021-02-24). "北京地铁17号线南段年底开通".
- "北京地铁17号线力争年内全线开工 将打造成一体化设计标准示范线-千龙网·中国首都网".
- "北京地铁17号线二次环评公示 拟撤永安里北站_新闻频道_中华网".
- (2019-12-30). "确定了!北京地铁17号线,京港地铁公司运营".
- (2023-12-29). "地铁17号线北段等三条地铁线(段)开通试运营". [[Beijing Municipal Commission of Transport]].
- (2023-12-18). "年底见!17号线北段和16号线剩余段开通筹备中~". [[MTR Corporation#Beijing.
- (26 December 2025). "明日开通试运营!北京3条(段)地铁新线来啦". [[Beijing Daily]].
- "北京轨道交通线网再扩容,周六起运营线路总数增至30条".
- (2025-06-23). ""17号线中段迎重要进展,年底全线贯通运行全程只需66分钟".
- "17号线2020年开通南北段".
- "17号线 北京京港地铁有限公司".
- (2021-12-31). "北京今日开通9条地铁线(段) 3条主干线贯通南北".
- 孙宏阳 (Sun Hongyang). (2023-12-27). "@天通苑居民,地铁进城将多一种更快选择:17换10".
- "东边的朋友注意了!坐这条地铁新线,可以比原来快10分钟!".
- "『北京』3条地铁新线全部进入“跑图”阶段".
- (8 July 2025). "临时用地审批情况公示(地铁17号线广渠门外站与马圈地块一体化项目地铁工程施工项目)". Beijing Municipal Commission of Planning and Natural Resources.
- "地名公告". [[北京市规划和自然资源委员会]].
- (2021-07-19). "轨道交通17号线、19号线一期、昌平线南延一期工程沿线车站命名预案". Beijing Municipal Commission of Planning and Natural Resources.
- "17号线路网车站站间距信息".
- (2021-11-09). "地名公告>嘉会湖站".
- (Chinese) [http://roll.sohu.com/20110117/n302188085.shtml Roll.sohu.com] "CBD核心区地铁17号线地下步道规模空前" ''中证网'' 2011-01-17
- (2012-02-13). "北京6条地铁新线开始前期调研".
- (Chinese) [http://finance.sina.com.cn/roll/20120616/155712331974.shtml "北京再规划建设3号、12号、R2线三条新地铁线路" 中国质量新闻网] 2012-06-16
- (Chinese) [http://www.bjnews.com.cn/news/2012/06/16/205055.html "北京将再增3条新地铁" 《新京报》] 2012-06-16
- (Chinese) [http://news.hexun.com/2012-06-16/142538109.html "北京将再增3条新地铁" 新京报] 2012-06-16
- Construction was expected to begin in 2014 and Line 17 would have a total length of {{convert. 48.9. km. mi. link. (2016-01-07 2013-10-10)
- (2019-06-10). "地铁17号线将在2022年底试运行,全程21站".
- (May 4, 2016). "北京地铁17号线两站已开工 一车站将建最长站台".
- (2022-07-08). "北京市轨道交通第三期建设规划(2022-2027年)环境影响报告书(征求意见稿).pdf".
- (2024-02-02). "北京轨道交通R6线一期工程设计01合同段(总体总包)(方案设计、初步设计、施工图设计)招标公告".
- (2024-02-02). "北京轨道交通R6线一期工程设计02合同段(全线通信、信号系统工点设计)(方案设计、初步设计、施工图设计)招标公告".
- (2024-02-02). "北京轨道交通R6线一期工程设计03合同段(全线供电系统工点设计)(方案设计、初步设计、施工图设计)招标公告".
- (2024-02-02). "北京轨道交通R6线一期工程勘察01合同段(勘察)招标公告".
This article was imported from Wikipedia and is available under the Creative Commons Attribution-ShareAlike 4.0 License. Content has been adapted to SurfDoc format. Original contributors can be found on the article history page.
Ask Mako anything about Line 17 (Beijing Subway) — get instant answers, deeper analysis, and related topics.
Research with MakoFree with your Surf account
Create a free account to save articles, ask Mako questions, and organize your research.
Sign up freeThis content may have been generated or modified by AI. CloudSurf Software LLC is not responsible for the accuracy, completeness, or reliability of AI-generated content. Always verify important information from primary sources.
Report