Skip to content
Surf Wiki
Save to docs
arts/film

From Surf Wiki (app.surf) — the open knowledge base

Kudankulam Nuclear Power Plant

Nuclear power plant in India

Kudankulam Nuclear Power Plant

Summary

Nuclear power plant in India

FieldValue
nameKudankulam Nuclear Power Plant
imageKudankulam Nuclear Power Plant Unit 1 and 2.jpg
countryIndia
coordinates
costUnits 1 & 2: in 2001 prices
Units 3 & 4: {{INRConvert39849c2year2017mode=historical}} in 2017 prices
Units 5 & 6: {{INRConvert49621c2year2020mode=historical}} in 2020 prices
ownerNuclear Power Corporation of India
construction_beganUnit 1:
Unit 2:
Units 3 & 4:
Unit 5:
Unit 6:
commissionedUnit 1:
Unit 2:
decommissioned
np_reactors6
np_reactor_typePWR
np_reactor_supplierRosatom
ps_cooling_sourceLaccadive Sea
ps_thermal_capacity2 × 3000 MWth
ps_units_operational2 × 1000 MW (gross)
ps_units_uc4 × 1000 MW (gross)
ps_units_manu_modelVVER-1000/412
ps_electrical_capacity2000
ps_annual_generation* Unit 1: 7584.740 GWh (2023)
* Unit 2: 5988.250 GWh (2023) <ref>[https://pris.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current853 PRIS - Unit 2 Statistics]
ps_electrical_cap_fac68.27% (2020–21)
websiteNuclear Power Corporation of India

Units 3 & 4: in 2017 prices

Units 5 & 6: in 2020 prices Unit 2: Units 3 & 4: Unit 5: Unit 6: Unit 2:

  • Unit 2: 5988.250 GWh (2023)

Kudankulam Nuclear Power Plant (or Kudankulam NPP or KKNPP) is the largest nuclear power station in India, situated in Kudankulam in the Tirunelveli district of the southern Indian state of Tamil Nadu. Construction on the plant began on 31 March 2002, but faced several delays due to opposition from local fishermen. KKNPP is scheduled to have six VVER-1000 reactors built in collaboration with Atomstroyexport, the Russian state company and Nuclear Power Corporation of India Limited (NPCIL), with an installed capacity of 6,000 MW of electricity.

Unit 1 was synchronized with the southern power grid on 22 October 2013 and since then, has been generating electricity at its warranted limit of 1,000 MW.

The original cost of the two units was 13,171 crore, but it was later revised to 17,270 crore. The cost was revised again to ₹22,462 crore ($4.76 billion in USD 2001) in 2014 due to increased expenses related to Interest During Construction (IDC), labor costs, operational expenses, and the deployment of Russian specialists at Kudankulam.

Russia advanced a credit of 6,416 crore (US$0.97 billion) for both the units. Unit 2 attained criticality on 10 July 2016 and was synchronized with the electricity grid on August 29 of the same year.

In 2015, Nuclear Power Corporation Ltd (NPCIL) announced a price of 4.29/kW·h (6.4 ¢/kW·h) for energy delivered from Kudankulam nuclear power plant.{{cite news | access-date = 9 September 2015

The ground-breaking ceremony for construction of units 3 & 4 was performed on 17 February 2016. Due to technology changes, inflation and insistence of the supplier and operator for additional liability insurance the construction cost of units 3 & 4 amounted to twice the cost of units 1 & 2 and was later revised to be .{{cite web | archive-url =https://web.archive.org/web/20160310165918/http://articles.economictimes.indiatimes.com/2014-12-03/news/56685094_1_kudankulam-nuclear-power-plant-units-liability-issue | archive-date = 10 March 2016 | url-status = dead | access-date = 21 July 2016}}{{cite web | archive-url = https://web.archive.org/web/20141203164113/http://www.thehindu.com/news/national/kudankulam-units-3-4-cost-more-than-doubles-over-liability-issues/article6658451.ece | archive-date = 3 December 2014 | url-status = live | access-date = 21 July 2016}} A budget of has been approved for construction of Units 5 & 6.

History

Background

Kudankulum under construction, 14 April 2009

An intergovernmental agreement (IGA) on the project was signed on 20 November 1988 by the Prime Minister of India, Rajiv Gandhi and the Soviet head of state, Mikhail Gorbachev, for the construction of two reactors. The project remained in limbo for a decade due to the dissolution of the Soviet Union. There were also objections from the United States, on the grounds that the agreement did not meet the 1992 terms of the Nuclear Suppliers Group (NSG). M. R. Srinivasan, Atomic Energy Commission (AEC) Chairman from 1987 to 1990, called the project "a non-starter". However, the project was revived on 21 June 1998.

Construction

Construction began on 31 March 2002, with the Nuclear Power Corporation of India Ltd (NPCIL) predicting that the first unit would be operational in March 2007, instead of the original target of December 2007.

A small port became operational in Kudankulam on 14 January 2004. This port was established to receive barges carrying over-sized light water reactor equipment from ships anchored at a distance of 1.5 km. Until 2004, materials had to be brought in via road from the port of Thoothukudi, risking damage during transportation. In 2008, negotiations on building four additional reactors at the site began. Though the capacity of these reactors had not been declared, it was expected that the capacity of each reactor will be 1,200 MW (1.2 GW). The new reactors would bring the total capacity of the power plant to 6,800 MW (6.8 GW). These reactors never entered the planning phase after being proposed, mostly due to protests and due to other reasons. No such units are currently planned or under construction.

The ground-breaking ceremony for construction of third and fourth units was performed on 17 February 2016 and AERB authorised the first pour of concrete on 19 June 2017. Construction of the third and fourth units started on 29 June 2017. AERB granted excavation permit for Unit 5 and 6 in 14 November 2018 and concerete pour begun in 2020. Construction of units 5 and 6 commenced on 29 June 2021. Unit 5 is expected to be ready for commissioning in December 2026, while unit 6 is expected to be ready by September 2027.

Cyber-attack

In 2019, NPCIL confirmed identification of malware in the internet connected administrative network but said that the critical internal network was isolated. KKNPP officials had earlier termed reports on the cyber attack as false. The malware was linked to the North Korea based Lazarus Group.

Contract Details

Rosatom has been awarded the Engineering and Procurement (EP) contract for the Kudankulam Nuclear Power Plant, with the Indian side responsible for the construction and commissioning. This differs from the contract Rosatom was awarded in Bangladesh for Rooppur Nuclear Power Plant, which encompassed Engineering, Procurement, and Construction (EPC) as well as the commissioning of the plant.

The Indian firm Larsen and Toubro has been awarded the construction contract, which includes the development of the reactor building, reactor auxiliary building, turbine building, diesel generator building, and other buildings associated with safety.

Design and specification

The reactors are pressurised water reactor of Russian design, model VVER-1000/V-412 referred also as AES-92. Thermal capacity is 3,000 MW, gross electrical capacity is 1,000 MW with a net capacity of 917 MW.{{cite web | archive-url = https://web.archive.org/web/20160721014654/http://www.rosatom.ru/upload/iblock/0be/0be1220af25741375138ecd1afb18743.pdf | archive-date=21 July 2016| url-status = live | access-date = 21 July 2016}} Construction is by NPCIL and Atomstroyexport. The plant is the largest nuclear power generation complex in India producing a cumulative 2 GW of electric power. Both units are water-cooled, water-moderated Pressurized water reactors.{{cite web | access-date =1 June 2008 |archive-url = https://web.archive.org/web/20080515211047/http://www.npcil.nic.in/kapp.asp |archive-date = 15 May 2008}}

Operations

The first reactor of the plant attained criticality on 13 July 2013 and was connected to the grid three months later. It started commercial operation from 31 December 2014. The second unit achieved criticality on 10 July 2016 and was connected to the grid in August. Commercial operation started on 15 October 2016.

The Kerala State Electricity Board (KSEB) board members have approved signing of a power purchase agreement (PPA) with the Nuclear Power Corporation of India (NPCIL) for sourcing electricity from the Kudankulam nuclear power project (KKNPP).

Unit 1 was shut down in June 2015 for refuelling and annual maintenance. On 21 January 2016, the reactor restarted and was connected to grid on 30 January.{{cite news

Kudankulam Nuclear Power Project Site Director D. S. Choudhary stated on 26 January 2018 that units 1 and 2 of the nuclear plant had generated a combined total of 22,800 million units since they began functioning.

In October 2025, the Central electricity regulatory body granted permission to NPCIL to use 50MWe from Units 1 and 2 for the commissioning of units 3 and 4. According to the plant director, unit 3 is expected to be commissioned in 2026.

Opposition

People had been opposing the plant since its proposal in 1979. The proposal however, was halted because of the protests. It was brought back in 2000, and construction started under the government of Atal Bihari Vajpayee.

In 2011, thousands from the vicinity of the plant protested against it, fearing a nuclear disaster, in the wake of the Fukushima Daiichi nuclear disaster According to the protesters, evacuation of people in the event of a nuclear disaster would be impossible. According to S P Udayakumar, of the People's Movement Against Nuclear Energy, "the nuclear plant is unsafe". However, in 2012, the chief of India's nuclear energy programme, Dr Srikumar Banerjee, called the plant "one of the safest" in the world. In December 2012, The Hindu reported that hundreds of villagers in the region were largely ignorant of the risks and benefits of the plant.

A public interest litigation (PIL) was filed in 2011 with the Supreme Court asking for nuclear power development to be delayed until safety concerns were independently assessed. In May 2013, the Supreme Court ruled in favour of the plant, stating that the nuclear power plant was in the larger public interest.

In March 2012, nearly 200 anti-nuclear protesters were detained for a few hours by the police. The protesters were set to join protests objecting resumption of work of one of two 1 GW reactors, a day after the local government restarted work on the project.

There have also been rallies and protests in favour of commissioning this nuclear power plant.

On, 24 February 2012, Prime Minister Manmohan Singh blamed foreign NGOs for protests at the power plant. News agencies reported that three NGOs had diverted donations earmarked for religious and social causes to the protests, in violation of foreign exchange regulations.

Supporters of the power plant in Idinthakarai village have been targeted by opponents using improvised explosive devices.

The Church of South India and the National Council of Churches opposed the power plant and supported the protests against it. Supporters of the power plant and the government have alleged that the protest against the power plant was instigated by churches and funded by foreign sources. The protestors dismissed the allegation of foreign funding, but said that seeking support from church was "natural" as many protestors were Christian localities living in the vicinity of the Reactor.

Response from officials

Former chairman of Atomic Energy Commission of India Srinivasan said, "The Fukushima plant was built on a beach-front, but the Kudankulam was constructed on a solid terrain and that too keeping all the safety aspects in mind. Also, we are not in a tsunami prone area. The plants in Kudankulam have a double containment system which can withstand high pressure. At least 14,000 crore has been spent. If we don't operate the plant immediately, it will affect the economic stability of our country".

A centre panel constituted by the Government of India, which did a survey of the safety features in the plant, vouched for the safety of the Kudankulam reactors. Dr Muthunayagam, who headed the panel, said that the protesters asked for some documents which are not related to the safety of the reactor. Nuclear scientist and principal scientific adviser to the federal Government of India Rajagopala Chidambaram has said "We have learnt lessons from the Fukushima nuclear accident, particularly on the post-shut-down cooling system", and also added Fukushima nuclear accident should not deter or inhibit India from pursuing a safe civil nuclear programme.

The Tamil Nadu state government formed a four-member expert panel which submitted a report to the government after inspecting the safety features of the plant. The Tamil Nadu government in the wake of the acute power shortages in the state has ordered in favour of the commissioning of the plant.

Allocation of power

Government of India announced the power allocation from the two units of the reactor on 29 August 2013.

BeneficiaryPower (MW)
Tamil Nadu925 MW
Karnataka442 MW
Kerala266 MW
Puducherry67 MW
For commissioning of units 3 and 450 MW
Unallotted250 MW
Total2,000 MW

As of 1 December 2021, the government is considering to increase its capability to 6,000 MW, on completion of KKNPP-3 & 4 (2 x 1,000 MW) and KKNPP-5 & 6 (2 x 1,000 MW) which are presently under construction.

Kudankulam Alley

The town council of Volgodonsk, Rostov Oblast named a lane located next to the Atommash plant as Kudankulam Alley in November 2018. The plant, which is owned by Rosatom, manufactures equipment for the Kudankulam Nuclear Power Plant.

Units

PhaseUnit
No.ReactorStatusCapacity in MWeConstruction startFirst criticalityGrid ConnectionCommercial operationClosureNotesTypeModelNetGross
I1PWRVVER-1000917100031 March 200213 July 201322 October 201331 December 2014
2PWRVVER-100091710004 July 200210 July 201629 August 201631 March 2017
II3PWRVVER-1000917100029 June 2017
4PWRVVER-1000917100023 October 2017
III5PWRVVER-1000917100029 June 2021
6PWRVVER-1000917100020 December 2021

References

References

  1. [https://cag.gov.in/uploads/download_audit_report/2017/Report_No.38_of_2017_-_Performance_Audit_on_Kudankulam_Nuclear_Power_Project,Units_I_and_II_Department_of_Atomic_Energy.pdf Performance Audit on Kudankulam Nuclear Power Project, Units I and II] (original link). [https://web.archive.org/web/20241002131259/https://cag.gov.in/uploads/download_audit_report/2017/Report_No.38_of_2017-_Performance_Audit_on_Kudankulam_Nuclear_Power_Project,_Units_I_and_II_Department_of_Atomic_Energy.pdf Archived link]
  2. [https://pris.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=852 PRIS - Unit 1 Statistics]
  3. [https://pris.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=853 PRIS - Unit 2 Statistics]
  4. "Monthly Genration Reports Actual for Apr-2021 : Central Sector Nuclear". Central Electricity Authority.
  5. "Construction of unit 5 & 6 of India's largest nuclear power plant in Kudankulam commences".
  6. (2002-03-31). "PRIS – Albert's-1 – Reactor Details". Iaea.org.
  7. (2013-01-13). "Commercial operation of Kudankulam plant delayed further". [[Business Standard]].
  8. "The professor and the politics in anti-nuclear crucible".
  9. Subramanian, T.S.. (11 November 2016). "Kudankulam ready for more". Frontline.
  10. (2013-10-22). "Wait for Kudankulam power ends; unit 1 linked to grid". [[Business Line]].
  11. "Report of the Comptroller and Auditor General of India on Kudankulam Nuclear Power Project, Units I and II".
  12. (9 August 2013). "Ready to run". Frontline.
  13. (2024-12-11). "KUDANKULAM-2".
  14. (11 March 2020). "Nuclear Power Plants". Department of Atomic Energy, Government of India.
  15. [http://www.nti.org/db/nisprofs/russia/exports/rusind/react.htm Nuclear Exports to India from Russia] {{webarchive. link. (1 April 2007)
  16. "The Hindu Business Line : Kudankulam port becomes operational".
  17. Dmitry Sergeev. (1 February 2008). "Russia, India edge closer to major nuclear deal". Reuters.
  18. "India, Russia to sign deal on new nuclear reactors".
  19. (17 February 2016). "Bhoomi pooja performed for Kudankulam 3rd, 4th units". Zee Media Corporation Ltd..
  20. (2024-12-11). "KUDANKULAM-4".
  21. (5 September 2019). "Make in India push: India likely to produce nuclear fuel with Russia's help".
  22. "e-Newsletter, October – December 2018".
  23. (23 June 2017). "AERB grants FPC clearance for Kudankulam units 3 and 4".
  24. (30 October 2019). "Confirmed: North Korean malware found on Indian nuclear plant's network". [[ZDNet]].
  25. (2024-09-03). "Rosatom issues clarification on Rooppur plant; says it never discloses project cost".
  26. (2021-02-18). "L&T Construction to build two units of Kudankulam nuclear power project". [[Mint (newspaper).
  27. "NPCIL to go into details with 4 reactor suppliers".
  28. "Nuclear Power Plant Type".
  29. (24 April 2012). "Koodankulam to start production in 40 days".
  30. "History of the Kudankulam Project".
  31. (2013-07-14). "Kudankulam nuclear plant goes critical". India Info Online.
  32. (2024-12-11). "KUDANKULAM-1".
  33. Sudhakar, A.. (7 June 2014). "Kudankulam reactor attains full capacity". The Hindu.
  34. "Nuclear Power in India | Indian Nuclear Energy - World Nuclear Association".
  35. (15 October 2016). "Путин и Моди запустили второй энергоблок АЭС "Куданкулам"".
  36. (2024-12-11). "KUDANKULAM-2".
  37. (28 January 2018). "Kudankulam nuclear reactors generated 22,800 million units".
  38. (6 June 2022). "A decade on, Kudankulam nuclear plant protesters say still face ordeal".
  39. Rahul Bedi. (28 October 2011). "Indian activists fear nuclear plant accident". [[The New Zealand Herald]].
  40. "Thirteen Reasons Why We Do Not Want the Koodankulam Nuclear Power Project".
  41. (12 April 2012). "Kudankulam one of safest reactors, Lanka's fears unfounded: India's nuclear chief". NDTV.
  42. (2 December 2012). "At Kudankulam's core is fear, ignorance and anger".
  43. Siddharth Srivastava. (27 October 2011). "India's Rising Nuclear Safety Concerns". Asia Sentinel.
  44. Ranjit Devraj. (25 October 2011). "Prospects Dim for India's Nuclear Power Expansion as Grassroots Uprising Spreads". Inside Climate News.
  45. (6 May 2013). "Kudankulam verdict: for this village, renewed protests or tacit acceptance". NDTV.
  46. (20 March 2012). "Nearly 200 arrested in India nuclear protest". France24.
  47. (16 February 2012). "Rally seeks power generation at Kudankulam plant". The Hindu.
  48. (24 February 2012). "Blood donation camp in support of N-plant". The Hindu.
  49. (24 February 2012). "5 NGOs diverted foreign funds to fuel Kudankulam stir". hindustantimes.
  50. (25 February 2012). "Kudankulam protests: 3 NGOs lose licence for diverting funds".
  51. Sudipto Mondal. "Explosions at village near Kudankulam plant: Reports".
  52. (22 November 2012). "Churches back Kudankulam stir". The Hindu.
  53. (9 February 2013). "The professor and the politics in anti-nuclear crucible". The Telegraph.
  54. (14 November 2011). "Kudankulam plant is safe: Srinivasan". [[The Times of India]].
  55. (19 November 2011). "Kudankulam reactors safest: Central panel". The Hindu.
  56. (12 March 2012). "R. Chidambaram bats for Kudankulam". The Hindu.
  57. (19 March 2012). "Kudankulam nuclear power plant issue ends – India – DNA". Dnaindia.com.
  58. [http://pib.nic.in/newsite/erelease.aspx?relid=98899 Press Information Bureau English Releases]. Pib.nic.in. Retrieved on 2013-12-06.
  59. "Now, a Kudankulam lane in Russia".
  60. (2021-06-30). "Construction of Kudankulam nuclear reactors 5 and 6 begins". The Hindu.
Wikipedia Source

This article was imported from Wikipedia and is available under the Creative Commons Attribution-ShareAlike 4.0 License. Content has been adapted to SurfDoc format. Original contributors can be found on the article history page.

Want to explore this topic further?

Ask Mako anything about Kudankulam Nuclear Power Plant — get instant answers, deeper analysis, and related topics.

Research with Mako

Free with your Surf account

Content sourced from Wikipedia, available under CC BY-SA 4.0.

This content may have been generated or modified by AI. CloudSurf Software LLC is not responsible for the accuracy, completeness, or reliability of AI-generated content. Always verify important information from primary sources.

Report