Skip to content
Surf Wiki
Save to docs
geography/france

From Surf Wiki (app.surf) — the open knowledge base

Flamanville Nuclear Power Plant

Nuclear power plant in Manche, France


Summary

Nuclear power plant in Manche, France

FieldValue
nameFlamanville Nuclear Power Plant
name_officialCentrale Nucléaire de Flamanville
imageFlamanville Nuclear Plant 2023.jpg
image_captionFlamanville NPP with the two P4 REP reactors on the right and the EPR on the left
coordinates
countryFrance
locationFlamanville, Manche, Normandy
statusUnits 1-3: Operational
construction_beganUnit 1: 1 December 1979
Unit 2: 1 May 1980
Unit 3: 3 December 2007
commissionedUnit 1: 1 December 1986
Unit 2: 9 March 1987
Unit 3: 21 December 2024
costUnit 3: €19.3 billion in 2015 prices
ownerEDF
operatorEDF
<!------------------------- NUCLEAR POWER STATIONS -->np_reactor_typePWR
np_reactor_supplierFramatome
ps_cooling_sourceEnglish Channel
ps_cooling_towers
ps_units_operational2 × 1330 MW, 1 × 1620 MW EPR
ps_units_manu_modelUnits 1–2: P4 REP 1300
Unit 3: EPR
ps_thermal_capacity2 × 3817 + 1 x 4300 MWth
ps_electrical_capacity4290
ps_electrical_cap_fac60.08% (2017)
70.55% (lifetime)
ps_annual_generation11.7 TWh (2023)
websiteCentrale nucléaire de Flamanville
https://www.edf.fr/centrale-nucleaire-flamanville3

Unit 2: 1 May 1980 Unit 3: 3 December 2007 Unit 2: 9 March 1987 Unit 3: 21 December 2024 Unit 3: EPR 70.55% (lifetime) https://www.edf.fr/centrale-nucleaire-flamanville3

The Flamanville Nuclear Power Plant is located at Flamanville, Manche, France on the Cotentin Peninsula. The power plant houses three pressurized water reactors (PWRs). Unit 1 and 2, rated 1.3 GWe each, and based on Westinghouse design, were ordered following the Messmer Plan and deliver full power since 1987. Unit 3 is an EPR unit with a nameplate capacity of 1.65 GWe connected to the grid in December 2024 and reached full power in December 2025. The power plant produced 18.9 TWh in 2005, which amounted to 4% of the electricity production in France. In 2006 there were 671 workers regularly working at the plant. In 2023, 11,7 TWh were produced with 1400 regular workers.

Construction of unit 3 began in 2007 with its commercial introduction scheduled for 2012. In charge Areva proved unable to manage this project (just like Olkiluoto 3), leading to the ultimate demise of the company. Various safety problems have been raised, including weakness in the steel used in the reactor. In July 2019, further delays were announced, pushing back the commercial introduction date to the end of 2022. the project was more than five times over budget. In January 2022, more delays were announced, with fuel loading continuing until mid-2023, and again in December 2022, delaying fuel loading to early 2024. Fuel loading was completed in May 2024.{{Cite news | access-date=1 August 2024

Unit 1 & 2

History

During the 1970s, Flamanville was one of the proposed construction sites for the French civil nuclear program. A 1975 poll of local inhabitants showed 63.7% in favor of the project.

Following a public inquiry, the formal declaration of public utility was published in 1977, in time for a January 1978 groundbreaking. The official start of construction was recorded as December 1979 for Unit 1 and May 1980 for Unit 2. First criticality was achieved in September 1985 and June 1986, with connections to the grid in December 1985 and July 1986 and full commercial operation in December 1986 and March 1987.

Characteristics

Units 1 and 2 are Generation II pressurized water reactors of hybrid design, with a nuclear island of type P4 and the conventional / turbine island of type P'4.

The reactor coolant systems (reactor vessel, steam generators, reactor coolant pumps) were furnished by Framatome. The two turbine islands (steam turbines, turbogenerators, auxiliary systems, and secondary-side pumps) were provided by Alstom.

Each reactor can produce 3,817 MWt. Gross electric power from the generator is 1,382 MWe, and net electric power, after station consumption, is 1,330 MWe, for a thermal efficiency of 34.8%. In 2025, Units 1 and 2 employed approximately 1,100 EDF employees and contractors, and supplied more than half the electricity required in the Normandy region.

Unit 3

Construction on a new reactor, Flamanville 3, began on 4 December 2007.{{Cite news | access-date=19 March 2011 | archive-url=https://web.archive.org/web/20141014020153/http://www.world-nuclear-news.org/newsarticle.aspx?id=14496 | archive-date=14 October 2014 | url-status=dead

On 3 December 2012, EDF announced that the estimated costs have escalated to €8.5 billion ($11 billion), and the completion of construction was being delayed to 2016. The next day the Italian power company Enel announced it was relinquishing its 12.5% stake in the project, and five future EPRs. They would be reimbursed for their project stake of €613 million plus interest.

In November 2014, EDF announced that completion of construction was delayed to 2017 due to delays in component delivery by Areva.

In April 2015, Areva informed the French nuclear regulator, Autorité de sûreté nucléaire (ASN), that anomalies had been detected in the reactor vessel steel, causing "lower than expected mechanical toughness values". Segolene Royal, Minister of Ecology, Sustainable Development and Energy in the Second Valls Government, asked the producer for further details and possible consequences.

Various safety problems have been raised, including weakness in the steel used in the reactor together with heterogeneity of the steel alloy forged high integrity components used in the reactor pressure vessel, that have also been shown to be present in Japanese-sourced components that have entered the French nuclear equipment supply chain. The safety of the Flamanville EPR plant has also been questioned due to the danger of flooding of the kind experienced during the 1999 Blayais Nuclear Power Plant flood. In June 2015 multiple faults in cooling system safety valves were discovered by ASN.

In September 2015, EDF announced that the estimated costs had escalated to €10.5 billion, and the start-up of the reactor was delayed to the fourth quarter of 2018. The delays of Unit 3 of Flamanville received additional attention when in December 2016 The Economist reported that the British loan guarantees for Hinkley Point C require Unit 3 to be operational by 2020, that the regulator will rule on the future of Unit 3 mid-2017 and that one possible outcome of this ruling can delay its opening far beyond 2018, thus jeopardizing the British loan guarantees thereby preventing EDF from building the EPRs at Hinkley Point.

In February 2017, renewed delays in the construction of the EPR-reactors at Taishan Nuclear Power Plant prompted EDF to state that Flamanville 3 remains on schedule to start operations by the end of 2018, assuming it receives regulator approval. In June 2017, the French regulator issued a provisional ruling that Flamanville 3 is safe to start.

In January 2018, cold functional tests were completed. In February, EDF found that some secondary cooling circuit welds did not meet specifications, causing EDF to carry out further checks and issue a report. Following this, ASN requested EDF to extend the welding checks to other systems. Hot functional tests had to be postponed.

In July 2018, EDF further delayed fuel loading to Q4 2019 and increased the project's cost estimate by a further €400 million ($467.1 million USD). The latest project cost estimates by EDF amounted to €10.9 billion ($12.75 billion USD), three times the original cost estimates. Hot testing was pushed back to the end of 2018. In January 2019, a further one-month delay in hot testing was announced.

In June 2019, the regulator ASN determined that eight welds in steam transfer pipes passing through the two-wall containment, that EDF had hoped to repair after startup, must be repaired before the reactor is commissioned. On 29 June 2019, it was announced that the start-up was once again being pushed back, making it unlikely it could be started before the end of 2022. It is estimated the repairs will add €1.5 billion to the costs, bringing the total to €12.4 billion. Further cost increases due to additional time needed to repair 110 defective welds have increased the cost to €12.7 billion.

In July 2020, the French Cour des Comptes finalised an eighteen-month in-depth analysis of the project, concluding that the total estimated cost reaches up to €19.1 billion. The severe delays incurred additional financing costs, as well as added taxes and levies. In a response, EDF did not dispute the findings of the court. In the same month, France's energy minister Barbara Pompili noted the high costs and delays, calling the project "a mess".

In December 2022, EDF announced a further delay of at least six months with an estimated cost increase of €500 million due to more work to establish a new process for the stress relieving heat treatment of some welds close to sensitive equipment. Estimated total costs increased to €13.2 billion. Fuel loading started on 8 May 2024 and has been completed on 22 May 2024.

On 3 September 2024, the reactor started test operation, but the following day it shut down automatically, possibly due to a configuration error. The reactor suffered a second automatic shutdown on September 17.

On 21 December 2024, the reactor was connected to the national grid, initially producing 100 MW of power. After commissioning tests during the first year of operation, the reactor reached 100% full power for the first time on 14 December 2025.

Incidents

On 9 February 2017, a mechanical problem with a fan in the turbine hall of unit 1 caused an explosion and fire, causing five people to be treated for smoke inhalation. While the non-nuclear accident did not cause any radioactive leak, it did cause the number one reactor to be disconnected from the power grid. EDF initially estimated the reactor would be operational within a week, but later estimated the end of March.

Units 1 and 2 were under enhanced surveillance by regulator Autorité de sûreté nucléaire (ASN) from 2019 to 2022 because of shortcomings in some operating activities, a high number of maintenance faults, poor mastery of certain maintenance operations, and inadequate quality of the ten-year inspection documentation of unit 1. This involved about 30 ASN inspections a year.

References

References

  1. (August 2025). "Nucléaire : la pleine puissance de l'EPR de Flamanville repoussée d'ici la fin de l'automne".
  2. (1976). "Westinghouse sells French nuclear stake". Chemical & Engineering News.
  3. "Edf: Update on the Flamanville EPR: the reactor produces its first electrons on the national electricity grid".
  4. (2024). "La centrale nucléaire de Flamanville".
  5. Jennifer Rankin. [https://www.theguardian.com/environment/2016/jul/27/flamanville-france-edf-nuclear-reactor-hinkley-point-c Flamanville: France's beleaguered forerunner to Hinkley Point C], ''The Guardian'', 27 July 2016.
  6. (29 July 2019). "Snag-hit new French nuclear power station delayed by further 3 years". Agence France Presse.
  7. (9 October 2019). "EDF warns of added costs of Flamanville EPR weld repairs".
  8. (5 September 2024). "France's newest nuclear reactor shuts itself down". France 24.
  9. "PRIS - Reactor Details. Flamanville Unit 1".
  10. "PRIS - Reactor Details. Flamanville Unit 2".
  11. (2021). "Poursuite de fonctionnement des réacteurs n°1 et n°2 de la centrale nucléaire de Flamanville après leur deuxième réexamen periodique".
  12. (2012). "Arabelle Steam Turbine for Nuclear Power Plant".
  13. "Alstom confirme sa position de leader pour les îlots conventionnels de centrale nucléaire".
  14. (2025-05-20). "La centrale nucléaire de Flamanville 1-2". EDF FR.
  15. (6 December 2007). "Flamanville 3 concrete poured". Nuclear Engineering International.
  16. (2020-07-09). "" Echec opérationnel " et " dérive des coûts " : la gestion de l'EPR, réacteur nucléaire de troisième génération, décriée par la Cour de comptes". Le Monde.fr.
  17. (3 December 2012). "Le coût de l'EPR de Flamanville encore revu à la hausse".
  18. (6 December 2012). "Enel Drops Participation in Flamanville EPR as Project Costs Soar by $2.6B". POWER.
  19. (4 December 2012). "Enel and Edf Terminate their cooperation on EPR in France". Enel.
  20. Michael Stothard. (18 November 2014). "EDF in fresh delay for flagship nuclear plant". Financial Times.
  21. (7 April 2015). "Flamanville EPR vessel anomalies under scrutiny". World Nuclear News.
  22. http://www.asn.fr: [http://www.asn.fr/Informer/Actualites/EPR-de-Flamanville-anomalies-de-fabrication-de-la-cuve Anomalies de fabrication de la cuve de l’EPR de Flamanville]. Communiqué de presse, 7 April 2015
    1. April 2015: [http://www.greenetvert.fr/2015/04/08/nucleaire-une-nouvelle-anomalie-detectee-sur-lepr-de-flamanville/82548 Nucléaire: une nouvelle anomalie détectée sur l’EPR de Flamanville]
  23. Jennifer Rankin. Flamanville: France's beleaguered forerunner to Hinkley Point C, ''The Guardian'', 27 July 2016.
  24. "Review: Irregularities and Anomalies Relating to the Forged Components of le Creusot Forge, 26 September 2016".
  25. "Review: Irregularities and Anomalies Relating to the Nuclear Reactor Primary Coolant Circuit Components Installed in Japanese Nuclear Power Plants - Part 1 French Carbon Anomaly Correlation to Japanese Nuclear Power Plants=24 October 2016".
  26. "Review: Irregularities and Anomalies Relating to the Nuclear Reactor Primary Coolant Circuit Components Installed in Japanese Nuclear Power Plants - Concluding Parts 2 & 3 - Potential Flawed Components Resident in Japanese Nuclear Power Plants=10 December 2016".
  27. [http://deciphering-fukushima.blogs.sciencesetavenir.fr/tag/monique%20sen%C3%A9 The great lesson France has to learn from Fukushima] Deciphering Fukushima, published 2011-03-08, accessed 8 May 2012
  28. Henry Samuel. (9 June 2015). "Faulty valves in new-generation EPR nuclear reactor pose meltdown risk, inspectors warn". Daily Telegraph.
  29. . (September 3, 2015). ["Flamanville EPR: optimised project management and a new timetable"](https://www.edf.fr/en/edf/flamanville-epr-optimised-project-management-and-a-new-timetable). *EDF*.
  30. (3 December 2016). "France's nuclear-energy champion is in turmoil". [[The Economist]].
  31. (22 February 2017). "EDF confirms Flamanville timetable after Taishan EPR delay". [[Times of India]].
  32. (28 June 2017). "French regulator says Flamanville 3 is safe to start".
  33. "Flamanville EPR completes key pre-operational tests - World Nuclear News".
  34. (4 June 2018). "Possible reprieve for Fessenheim due to further Flamanville delays". Nuclear Engineering International.
  35. (20 June 2019). "Nucléaire : l'EPR de Flamanville connaît de nouveaux retards et ne pourra pas démarrer avant 2022".
  36. (9 October 2019). "EDF warns of added costs of Flamanville EPR weld repairs". World Nuclear News.
  37. (25 January 2019). "EDF gives update on Flamanville 3". Nuclear Engineering International.
  38. (20 June 2019). "Weld repairs to delay Flamanville EPR start-up". World Nuclear News.
  39. Boselli, Muriel. (12 January 2022). "EDF delays Flamanville start-up to end 2023 on weld issue".
  40. (2022-01-12). "Point d'actualité sur l'EPR de Flamanville".
  41. Eales, Chris. (23 July 2020). "French "EPR is a mess" – energy minister". Montel News.
  42. (19 December 2022). "Further delay to Flamanville EPR start up". World Nuclear News.
  43. EDF. (2024-05-08). "EDF: Update on the Flamanville EPR".
  44. (24 May 2024). "Fuel loading completed at France's Flamanville 3 EPR".
  45. (10 September 2024). "Flamanville EPR in automatic shut down". Nuclear Engineering International.
  46. (17 September 2024). "France's EDF investigates second automatic shutdown at Flamanville 3 reactor". Reuters.
  47. (21 December 2024). "France's Most Powerful Nuclear Reactor Finally Comes On Stream". Barrons.
  48. (4 August 2025). "Delay in Flamanville 3 attaining full power".
  49. (14 December 2025). "Flamanville 3 attains full power".
  50. Dearden, Lizzie. (9 February 2017). "French nuclear power plant explosion: 'Several injured' after blast in Flamanville".
  51. (9 February 2017). "Incendie à la centrale nucléaire de Flamanville : ce que l'on sait".
  52. Vaughan, Adam. (21 February 2017). "EDF faces £1m a day bill to keep French nuclear reactor offline". The Guardian.
  53. (7 July 2022). "ASN lifts its enhanced monitoring of Flamanville 1 and 2". Nuclear Engineering International.
Wikipedia Source

This article was imported from Wikipedia and is available under the Creative Commons Attribution-ShareAlike 4.0 License. Content has been adapted to SurfDoc format. Original contributors can be found on the article history page.

Want to explore this topic further?

Ask Mako anything about Flamanville Nuclear Power Plant — get instant answers, deeper analysis, and related topics.

Research with Mako

Free with your Surf account

Content sourced from Wikipedia, available under CC BY-SA 4.0.

This content may have been generated or modified by AI. CloudSurf Software LLC is not responsible for the accuracy, completeness, or reliability of AI-generated content. Always verify important information from primary sources.

Report