From Surf Wiki (app.surf) — the open knowledge base
Darbandikhan Dam
Dam in Darbandikhan, Kurdistan, Iraq
Dam in Darbandikhan, Kurdistan, Iraq
| Field | Value |
|---|---|
| name | Darbandikhan Dam |
| image | Darbandikhan Dam USACE NWD.jpg |
| image_caption | Upstream side of the dam and spillway |
| location_map | Iraq |
| coordinates | |
| country | Iraq |
| Kurdistan Region | |
| location | Darbandikhan (65 km southeast of Silêmani, Kurdistan Region) |
| status | O |
| construction_began | 1956 |
| opening | 1961 |
| owner | Ministry of Water Resources |
| dam_type | Embankment; rock-fill, central clay core |
| dam_height | 128 m |
| dam_length | 445 m |
| dam_width_crest | 17 m |
| dam_volume | 7100000 m3 |
| dam_elevation_crest | 495 m |
| dam_crosses | Sirwan River |
| spillway_type | Controlled chute |
| spillway_capacity | 11400 m3/s |
| res_capacity_total | 3000000000 m3 |
| res_capacity_active | 2500000000 m3 |
| res_capacity_inactive | 500000000 m3 |
| res_catchment | 17850 km2 |
| res_surface | 113 km2 |
| res_elevation | 485 m |
| plant_hydraulic_head | 80 m (rated) |
| plant_commission | 1990 |
| plant_turbines | 3 x 83 MW Francis-type |
| plant_capacity | 249 MW |
Kurdistan Region The Darbandikhan Dam () is a multi-purpose embankment dam on the Diyala River in northern Sulaymaniyah Governorate, Iraq. It was constructed between 1956 and 1961. The purpose of the dam is irrigation, flood control, hydroelectric power production and recreation. Due to poor construction and neglect, the dam and its 249 MW power station have undergone several repairs over the years. A rehabilitation of the power station began in 2007 and was completed in 2013.
Background
After the Harza Engineering Company of USA designed the dam, construction began in 1956. The reservoir began to fill in November 1961 and the dam was complete that same year. After the reservoir filled, several problems occurred. In 1967, there was a major slope failure about 100 m upstream of the dam. This and other slope failures are continually under repair. The bedrock beneath the dam has to be re-grouted and the crest of the dam settled too much, required it to be repaired. The rip-rap on the upstream face of the dam was also repaired in 1999 and 2000.
Between 1983 and 1985 the dam's power station was replaced by German (Polensky & Zöllner) and Japanese companies (Mitsui). The original 2 × 800 kW generators were replaced with the current power plant's 83 MW generators. The generators were commissioned in 1990 after the political situation in the country calmed. However, two of the generators were not commissioned correctly and the turbines suffered from severe cavitation. New spillway gates were installed between 1989 and 1990 after they were removed in 1988 because of the Iran–Iraq War. During the war, the spillway and substation were damaged from bombing. The power station was damaged from bombing in 1990 as well. In 2007, the World Bank began a US$35.36 million project to repair the Darbandikhan and Dokan Dams. Repairs to the Darbandikhan Dam cost $18.85 million and were completed in 2013 resulting in 100 percent power availability.
Design and operation

The dam is located within a gorge on a foundation of sedimentary rocks. It is a rock-fill embankment type with a central clay core. The dam is 128 m tall and 445 m long (535 m if the spillway section is included). Its crest is 17 m wide and at an elevation of 495 m. The structural volume of the dam including rock, clay and filters is 7100000 m3. The dam collects water from a catchment area that covers 17850 km2. Its reservoir, by design, has a storage capacity of 3000000000 m3. Of that capacity, 2500000000 m3 is active (or useful) storage while 500000000 m3 is dead storage. At a normal elevation of 485 m, the reservoir covers an area of 113 km2.
To protect the dam from flooding, it is equipped with a controlled chute spillway on its right bank. It is controlled by three 15 m x 15 m tainter gates. At the terminus of each chute there is a ski-jump to help dissipate energy. The maximum discharge capacity of the spillway is 11400 m3/s. The dam's power plant is located at its toe and contains 3 x 83 MW Francis turbine-generators. They are each afforded a rated hydraulic head of 80 m and can each discharge 113 m3/s. Above the tail-race for each turbine is an irrigation outlet. Each of the three outlets can discharge up to 175 m3/s downstream.
References
References
- "دوو بەنداوە گەورەكەی كوردستان ژمارەیەكی نوێیان تۆماركرد". Rûdaw.
- "Otomobîlek ket Bendava Derbendîxanê: Dayik û kur xeniqîn". Rûdaw.
- (31 July 2006). "Dokan and Derbendikhan Dam Inspections". World Bank.
- (6 June 2003). "Iraqi Dam Assessments". United States Army, Corps of Engineers.
- "Dokan and Derbandikhan Emergency Hydro Power Project". World Bank.
- (26 June 2015). "ICR Review: Dokan And Derbandikhan Emergency Hydro Power Project". IEG.
This article was imported from Wikipedia and is available under the Creative Commons Attribution-ShareAlike 4.0 License. Content has been adapted to SurfDoc format. Original contributors can be found on the article history page.
Ask Mako anything about Darbandikhan Dam — get instant answers, deeper analysis, and related topics.
Research with MakoFree with your Surf account
Create a free account to save articles, ask Mako questions, and organize your research.
Sign up freeThis content may have been generated or modified by AI. CloudSurf Software LLC is not responsible for the accuracy, completeness, or reliability of AI-generated content. Always verify important information from primary sources.
Report