Skip to content
Surf Wiki
Save to docs
general/natural-gas-fields-in-uzbekistan

From Surf Wiki (app.surf) — the open knowledge base

Kandym–Khausak–Shady–Kungrad project


The Kandym–Khausak–Shady–Kungrad project is a project to develop natural gas fields in Uzbekistan. The project is carried out by a consortium of Lukoil (90%) and the Uzbekneftegaz (10%).{{Cite journal |archive-date = 2017-10-28 |archive-url = https://web.archive.org/web/20171028221737/http://www.oilru.com/or/34/653/ |url-status = dead | archive-url= https://web.archive.org/web/20110722031926/http://www.neurope.eu/articles/78854.php | archive-date= 2011-07-22 | url-status= dead

History

The production sharing agreement on the project was signed between Lukoil and Uzbekneftegaz on 16 June 2004 in Tashkent in the presence of the presidents of Russia and Uzbekistan. The agreement came into force on 24 November 2004 and will be in force until 2039.{{cite news | archive-url= https://web.archive.org/web/20061009100743/http://www.turkishweekly.net/news.php?id=34271 | archive-date= 2006-10-09 | url-status= dead

On 8 September 2005, the agreement on creating a consortium comprising Uzbekneftegaz, Lukoil, Petronas, Korea National Oil Corporation and China National Petroleum Corporation was signed in Tashkent.

The drilling of development wells in the Khausak gas field started on 1 July 2006. The Khausak field was inaugurated on 29 November 2007. | archive-url= https://archive.today/20130201064350/http://uk.reuters.com/article/oilRpt/idUKL2987617820071129 | url-status= dead | archive-date= February 1, 2013

In March 2012, Lukoil signed a deal with a consortium of banks for a loan of up to US$500 million for the development.

Development

Confirmed geological reserves of natural gas in the project area amount to 329 e9m3. It is expected that the project will produce 207 e9m3 of gas over its lifetime with maximum annual output of 11 e9m3, expected to reach by 2013. Lukoil is aiming for peak gas production at Kandym-Khauzak-Shady of around 47 Moilbbl/a of oil equivalent in 2018.

The project comprises a gas processing plant, plans for drilling more than 170 production wells and construction of 1500 km of pipelines. In addition, the project foresees construction of two compressor plants, gas gathering stations, shift camps, high-voltage power transmission lines and a separate 1400 km long railroad track, motorways and access roads.

References

Info: Wikipedia Source

This article was imported from Wikipedia and is available under the Creative Commons Attribution-ShareAlike 4.0 License. Content has been adapted to SurfDoc format. Original contributors can be found on the article history page.

Want to explore this topic further?

Ask Mako anything about Kandym–Khausak–Shady–Kungrad project — get instant answers, deeper analysis, and related topics.

Research with Mako

Free with your Surf account

Content sourced from Wikipedia, available under CC BY-SA 4.0.

This content may have been generated or modified by AI. CloudSurf Software LLC is not responsible for the accuracy, completeness, or reliability of AI-generated content. Always verify important information from primary sources.

Report