From Surf Wiki (app.surf) — the open knowledge base
Elektrėnai Power Plant
Power plant in Elektrėnai, Lithuania
Power plant in Elektrėnai, Lithuania
| Field | Value |
|---|---|
| name | Elektrėnai Power Plant |
| image | Elektrėnai Power Plant in Elektrėnai, Lithuania by Augustas Didžgalvis 2.jpg |
| coordinates | |
| name_official | Elektrėnų kompleksas |
| country | Lithuania |
| location | Elektrėnai |
| status | Operational |
| construction_began | 1960 |
| commissioned | 1972 |
| owner | Ignitis |
| operator | Ignitis Gamyba AB |
| th_fuel_primary | Natural gas |
| th_fuel_secondary | Heavy fuel oil |
| ps_units_operational | 2 × 300 MW, 1 × 455 MW |
| ps_electrical_capacity | 1055 MW |
| website |
The Elektrėnai Power Plant or Elektrėnai Complex () is a gas- and fuel-oil-fired 1,055 MW electricity generating station near Elektrėnai, Lithuania, about 50 km west of the capital, Vilnius. It is operated by Ignitis gamyba AB, a subsidiary of Ignitis.
History
.jpg)
The plant was built in stages between 1960 and 1972. The Strėva River was dammed to supply it with cooling water, creating the Elektrėnai Reservoir. In 2008, the plant comprised eight units fired with natural gas. In the past, it used heavy fuel oil and, for a brief period in 1990s, a bitumen-based fuel known as Orimulsion imported from Venezuela. It was designed as a base load plant, and generated about 10 TWh per year until 1992. Its operations were then reduced to about 5% of its capacity, since it acted only as a reserve in the Lithuanian power system.
After the shutdown of the Ignalina nuclear power plant in 2009, the plant became the primary source of Lithuania's electrical power. Since the plant did not meet European Union environmental guidelines, improvement projects have been proposed. A flue-gas desulfurization project was completed in September 2008. In December 2007, Ministry of Economy announced that a new 400 MW combined cycle unit would be built at the site as well. The cost of the new unit was estimated at 252 million euros; 57% of the funding was planned to be supplied by the European Union, 33% by the plant, and the remaining 10% by the National Ignalina Decommissioning Fund. In 2012, a 9th unit was opened, which cost 377 million euros. It was built by a Spanish company Iberdrola Ingenieria y Construccion.
The plant supplies district heating to the town of Elektrėnai, established in 1962, originally to support its workers.
Units
| Unit | Commissioned | Power | Status |
|---|---|---|---|
| 1 | 30 December 1962 | 150 MW | Decommissioned |
| 2 | 4 November 1963 | 150 MW | Decommissioned |
| 3 | 12 September 1964 | 150 MW | Decommissioned |
| 4 | 18 August 1965 | 150 MW | Decommissioned |
| 5 | 22 June 1967 | 300 MW | Decommissioned |
| 6 | 30 June 1968 | 300 MW | Decommissioned |
| 7 | 29 December 1971 | 300 MW | Inactive; in reserve |
| 8 | 28 September 1972 | 300 MW | Inactive; in reserve |
| 9 | 23 October 2012 | 455 MW | Active |
References
References
- "Elektrėnai Complex".
- (2010-04-19). "Environmental upgrade for Lithuanian Power Plant". [[European Bank for Reconstruction and Development]].
- (2007-12-20). "EU grants EUR 50 mln for upgrading of Lithuanian Power Plant". Lithuania in the European Union.
- "Atidarytas 1,3 MLRD. Litų kainavęs Lietuvos elektrinės blokas".
- "Lietuvos elektrinė". [[Universal Lithuanian Encyclopedia]].
- (29 June 2024). "Inside Lithuania’s strategic power plant".
This article was imported from Wikipedia and is available under the Creative Commons Attribution-ShareAlike 4.0 License. Content has been adapted to SurfDoc format. Original contributors can be found on the article history page.
Ask Mako anything about Elektrėnai Power Plant — get instant answers, deeper analysis, and related topics.
Research with MakoFree with your Surf account
Create a free account to save articles, ask Mako questions, and organize your research.
Sign up freeThis content may have been generated or modified by AI. CloudSurf Software LLC is not responsible for the accuracy, completeness, or reliability of AI-generated content. Always verify important information from primary sources.
Report